Department of Veterans Affairs
Program Guide PG-18-14
Office of Facilities Management
Chapter - 220
December 2004
ROOM FINISHES, DOOR AND HARDWARE SCHEDULE
Service - Credit Union
ROOM OR SPACE
DOORS
HARDWARE
FLOOR
BASE
WALLS
WAINS
CEILING
DOOR
H.W.NO.
SYMBOL
GWB1,2
Itinerant Offices
CP
RB
AT
1/2 S-T
52
GWB1,2
Full Office
CP
RB
AT
1/2 S-T
157
63
GWB1
Corridor
VCT
RB
AT
1/2 QQ-T
1
Full height partition to underside of structure above. See Design and Construction
Procedures PG-18-3, Topic 14."Physical Security Requirements and Options".
2
Pass through window wall; CMU. See Design and Construction Procedures PG-18-3, Topic
14."Physical Security Requirements and Options".
44