5)
Electrical Wiring and Connections:
a)
Wiring cut, abraded, loose at terminal, or not enclosed were
required.
b)
Adequate slack not provided for wiring to relieve strain, or
insulation stripped from wiring.
B.
Operational Test:
The utility system(s) should be completely assembled
and connected to the applicable water, electrical, gas, steam, HVAC
and drainage service. Energize the utilities and test in compliance
with the manufacturer's instructions to insure that the system(s)
conforms to the contract requirements. Nonconformance to the
specified operation should constitute failure and system(s) should be
rejected.
C.
Certification Compliance Examination:
Certifications, certified test reports,
or listing marks for codes and standards, as applicable, should be
examined and validated as proof of compliance.
1)
Utility Distribution System(s) should conform to the following
standards:
-
National Sanitation Foundation (NSF)
-
Underwriters Laboratories (UL)
-
National Electrical Manufacturers Association (NEMA)
-
National Fire Protection Association (NFPA)
-
American National Standards Institute (ANSI)
-
American Society for Testing and Materials (ASTM)
2)
Conformance to these standards should be evidence by seal,
label, stamp, or certified test reports.
11416-2