350
Plumbing Distribution: Target Costs
354
TARGET COSTS
354.1
RANGE
The cost target range for plumbing distribution is .00 to .00 per
OGSF, averaging about .30. These figures are slightly higher than the
cost base, but are considered justified by a much greater capacity for
future change than is the case with conventional design and construction.
See Section 751.2.5 for further discussion.
354.2
SCOPE
354.2.1
Included
Complete plumbing subsystem for the entire hospital beyond the central
plant, including:
1. Pressure lines: domestic cold water, domestic hot water, natural gas,
steam, distilled water, compressed air, sprinklers and standpipes;
2. medical gases: oxygen, medical compressed air, suction and nitrous
oxide;
3. gravity lines: soil, waste, condensate, vents and stormwater; and
4. equipment: pumps, motors, storage tanks, etc., which are not part of
the central plant and are required for plumbing distribution
354.2.2
Not Included
tanks, meters, etc.;
2. electrical work required in connection with plumbing distribution
equipment;
3. distribution required exclusively for the HVC subsystem such as chilled
water, heating hot water and steam for humidifiers and heat
exchangers; and
4. site work.
1 - 213