07-98
a. The Contractor shall prepare all graphics, tables, maps and
plans in support of the report's studies and recommendations. All plans shall
be on an 8 1/2 inch by 11 inch format.
b. The Contractor shall incorporate revisions to the draft
identified by VA. Unless otherwise specified, the number of copies of the
report to be prepared are:
ITEM
DELIVERY
QUANTITY
Draft Report
40 days after issuance
5 copies of Notice to
Proceed
Final Report
50 days after issuance
5 copies of Notice to
Proceed
c. All submissions are to be made to the Project Manager:
C.
EXPERIENCE AND QUALIFICATIONS:
1. Firm: The Contractor shall provide a brief history of the firm,
outlining the principal clients served by performing similar or related work,
the scope of such work and the date the work was accomplished.
2. Personnel: Identify by title and work experience the key personnel
to be committed to the work.
END