06-06
O. Room numbers and names shall be shown on HVAC plans at every review
stage including any schematic submissions. Where there is
insufficient room on HVAC floor plans to show room names, rooms
numbers only may be shown on the floor plan with the room numbers and
names tabulated on the drawing.
7.3 EQUIPMENT SCHEDULES
A. Equipment Schedules shall be listed in the following order,
vertically, from left to right, to facilitate checking and future
reference. Trade names or manufacturers model numbers shall not be
shown.
conditions for the various occupancies)
3. Air Flow Measuring Devices
4. Air Handling Equipment
5. Air Separators
6. Chillers, Condensing Units, Air Cooled Condensers
7. Convertors
8. Cooling Towers
9. Engineering Control Center (ECC)
10. Expansion Tanks
11. Fans
12. Fan-coil Units, Air Terminal Units (Boxes)
13. Filters for closed loop Water Systems (chilled water and hot
water)
15. Heat Recovery Equipment
16. Humidifiers
17. Pre-filter, after-filter (may be combined with pre-filters)
18. Preheat Coils, Cooling Coils, Reheat Coils
19. Pressure Reducing Valves, Safety Valves
20. Pumps
21. Radiant Panels
22. Room By Room Air Balance
23. Sound Attenuators
24. Supply, Return and Exhaust Air Diffusers and Registers
25. Unit Heaters
27. Water Flow Measuring Devices
28. Other Schedules As Required
25