May 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
DESIGN DEVELOPMENT 2
STEAM DISTRIBUTION REVIEW
COMMENTS/
NO.
ITEM
YES/NO/NA
1
Have A/E Submission Requirements (PG-18-15) for this review been
met? List omissions.
2
System Design complies with VA Outside Steam Distribution Design
Manual.
3
Are calculations complete including pipe and equipment sizing, steam
traps, thermal expansion, pipe stress?
4
Are Master Specs to be utilized of current issue?
5
Is all pipe stress within ASME B31.1 limits?
6
Do expansion joint movement requirements include safety factor?
7
Has adequate clearance been shown for maintenance access in
manholes and tunnels?
8
Have steam lines been shown in profile with proper slope and drip
traps?
9
Have warm-up bypasses been provided for all steam main gate valves?
10
Have drip pockets and steam traps been provided ahead of all steam
main gate valves?
11
Acceptable responses to previous comments?
12
Coordination with other disciplines
13
Compliance with VA National CAD Standard Application Guide and
applicable National CAD Standard modules.
5