HVAC RELATED A/E SUBMISSION REQUIREMENTS
(See VA A/E Submission Requirements, PG-18-15, Volume B, for Major New facilities, and Major Additions
and Renovations).
FINAL BID DOCUMENTS:
1.
Place the seal of the Registered Professional Engineer responsible for the design of the HVAC systems
on the bid documents.
2.
Submit revised draft specifications to incorporate all changes, resolution of conflicts, and modifications
noted at CD1 review, and results of any drawing changes not shown on CD1 documents that affect the
specifications.
3.
Type specifications in final format and submit for review along with full size final drawings fully
coordinated.
4.
Return draft specifications reviewed at CD1 review to aid final bid document review.
Contact Satish Sehgal @ 202-565-5032, Kurt Knight @ 202-565-4663, Don Walden 202-565-5014 or Sat
Gupta @ 202-565-5268 for additional information.
September 2001