HVAC RELATED A/E SUBMISSION REQUIREMENTS
(See VA A/E Submission Requirements, PG-18-15, Volume B, for Major New Facilities, and Major
Additions, and Renovations).
CONSTRUCTION DOCUMENTS 1 (CD1):
1.
Provide complete and final calculations of all HVAC equipment and systems.
2.
Submit sound analysis of various systems and steps taken to ensure compliance with the noise
criteria.
3.
Complete coordination with other disciplines by providing revised information developed since the last
submission.
4.
Submit 100% complete (1/8" scale) all HVAC floor plans. Separate plans for duct work and piping,
unless waived by VA.
5.
Submit 100% complete (1/4" scale) all mechanical equipment room floor plans with minimum two
cross sections at right angles to each other.
6.
Show all roof mounted equipment on roof plans.
7.
Update smoke and fire partitions on HVAC floor plans as described under DD1.
8.
Provide 100% complete drawings of the outside chilled and condenser water distribution with profiles,
sections, and details etc. Show existing utilities through actual inspection at the site and discussions
with the medical center.
9.
Provide 100% complete automatic temperature control drawings including point schedules for all trades,
a riser diagram showing locations of ECC, and field data gathering panels. Show actual location of ECC
and peripherals on floor plans.
10.
Provide 100% complete HVAC demolition drawings showing clearly the extent of demolition work.
11.
Submit HVAC original VA Master Specification drafts marked-up showing the editing for the project.
Assure the specification sections represent accurate coordination between drawings and specifications.