June 99
b. At ceiling of suspended gypsum board or plaster ceilings
c. At existing ceilings
7.
FINISHES:
7.1
Interior finishes are recommended in VA Program Guide
PG-18-14, Room Finishes, Door and Hardware Schedule.
The project management team must review any deviation
from this document prior to start of construction document
phase.
7.2
Combine the finish schedule and color design schedule
and include them on the drawings. Use the finish schedule
format included in Room Finishes, Door, and Hardware
Schedule (PG-18-14). Demolition plans must show the
existing finishes.
CEILINGS: All suspended acoustic tile ceilings, if
used, shall be
8.
600 by 600 mm (2 x 2) lay-in panels with regular edge in a
standard 25 mm (1") grid.
9.
LOW SLOPE ROOF SYSTEMS:
9.1
Low-slope roof systems include but are not limited to the
following roofing membranes with roof insulation:
a. Bituminous built-up roofing systems
b Modified bituminous roofing systems
c. Single-ply sheet roofing systems
d. Fluid-applied roofing systems
9.2
Design low slope roof systems in accordance with the
recommendations of the National Roofing Contractors
Association (NRCA) Roofing and Waterproofing Manual
and this Criteria.
9.3
Design all roofs with slope to roof drains or gutters.
9.4
Reroofed areas shall conform to this Article.
VA Design Guide -- National Cemetery Administration
Page 5 -6