06-06
9. Engineering Control Center (ECC)
10. Expansion Tanks
11. Fans
12. Fan-coil Units, Air Terminal Units (Boxes)
13. Filters for closed loop Water Systems (chilled water and hot
water)
15. Fume and Canopy Hoods
16. Heat Recovery Equipment
17. Humidifiers
18. Prefilter, afterfilter (may be combined with prefilters)
19. Preheat Coils, Cooling Coils, Reheat Coils
20. Pressure Reducing Valves, Safety Valves
21. Pumps
22. Radiant Panels
23. Room By Room Air Balance
24. Sound Attenuators
25. Supply, Return and Exhaust Air Diffusers and Registers
26. Unit Heaters
28. Water Flow Measuring Devices
29. Other Schedules As Required
B. Equipment performance and capacity data shall correspond to that
shown in the calculations, not a particular manufacturer's catalog
data, but the data shall be in the range of available manufactured
products.
C. Convertors, coils, pumps and chillers in glycol-water system shall be
identified on the equipment schedule showing the percent glycol by
volume of the circulating fluid for equipment de-rating purposes.
7.4 PIPING DRAWINGS
A. Avoid routing piping through rooms containing electrical or
communication equipment.
B. Branch piping serving each floor shall have shut-off valves at mains
to isolate branch.
C. Show sections or profiles of underground piping to show elevation
with respect to grade, roads and possible conflicting utilities,
including provision for draining and venting.
D. The quantity of rock excavation for HVAC work shall be shown on the
"MH" drawings.