June 2006
A/E CHECKLIST
TITLE________________________________PROJECT NO. ______________
LOCATION___________________________________DATE ______________
REVIEWED BY ___________________________________________________
ORGANIZATION _________________________________________________
FINAL CONSTRUCTION DOCUMENTS
STRUCTURAL REVIEW
COMMENTS/
NO.
ITEM
YES/NO/NA
1
Percent Complete
a. Drawings
b. Specifications
c. Calculations
2
Drawings (Spot Check) Comply with VA NCS Application Guide
a. Dimensions
b. Size of Beams
c. Size of Columns & Base Plates
d. Size of Steel Decking (Type & Properties)
e. Size of Floor Slab
d. Floor Depressions
g. Floor & Roof Openings
f. Elevation of Top of Beams
g. Composite beam/girder reaction shown
h. Shear Walls & Braced Bents Location
i. Expansion Joint Detail (Special attention in seismic. areas)
j. Construction Joints & Control Joints
k. Orientation of Columns
l. Grade Beam Detail
m. Typical Footing (Size & Detail, including Elevation)
n. Pile Cap (Detail including Cut-off Elevation)
o. Total Linear Feet of Piles/Caissons
p. Caisson (Detail including Elevation, Top & Bottom)
q. Rock Elevation (Assure classification with Soil Report)
r. Estimate of Quantity of Rock Excavation
s. Water Proofing Detail
t. Design Parameters (Floor Live Load, Wind, Seismic, & Soil
Bearing Pressure)
4